In an effort to keep our citizens aware, below is the tentative schedule for the 4th – 6th Street Sewer Improvements Project. We are sorry for the inconvenience that this has caused our residents. 

 

Week of August 25th - Pipe burst along Park Drive easement; Landscape restoration all homes along McIntosh Drive.

 

Week of September 1st – Complete last segment along Park Drive easement and tie into Sixth Street; Temporary asphalt patches all utility cuts along McIntosh Drive.

 

Week of September 8th - Pipe burst last segment at the intersection of Victory Drive and McIntosh Drive; Reinstate services.

 

Week of September 15th - Cleanup easement at the intersection of Victory Drive and McIntosh Drive; Complete final landscape restoration at easement and remaining houses. 

 

Week of September 22nd - Mill and overlay McIntosh Drive.

Facebook Twitter Email

Other News in Spotlight

2025 Property Tax Digest and 5-Year Millage History of Levy

2025 TAX DIGEST AND 5-YEAR MILLAGE HISTORY OF LEVY

Posted on: January 14, 2026 | Last Modified on: January 16, 2026