In an effort to keep our citizens aware, below is the tentative schedule for the 4th – 6th Street Sewer Improvements Project. We are sorry for the inconvenience that this has caused our residents.
Week of August 25th - Pipe burst along Park Drive easement; Landscape restoration all homes along McIntosh Drive.
Week of September 1st – Complete last segment along Park Drive easement and tie into Sixth Street; Temporary asphalt patches all utility cuts along McIntosh Drive.
Week of September 8th - Pipe burst last segment at the intersection of Victory Drive and McIntosh Drive; Reinstate services.
Week of September 15th - Cleanup easement at the intersection of Victory Drive and McIntosh Drive; Complete final landscape restoration at easement and remaining houses.
Week of September 22nd - Mill and overlay McIntosh Drive.